OKC traffic lanes shift as I-235 rebuilding nears fall completion

The Oklahoman

By Steve Lackmeyer

April 15, 2021 Another major shift in traffic is starting for the thousands of motorists who travel though the Interstate 235 and Interstate 44 junction as the $105 million project nears completion this fall. Reconstruction of I-235 between NW 23 and NW 63 started a decade ago and included widening the highway; the switch of two of the cloverleaf ramps at the junction to flyover bridges; new bridges and ramps at NW 36 and NW 50; and replacement of a railroad bridge over I-235. The first change will last about a week or two with the NW 63 exit from northbound I-235 moving from north of the junction to south of the junction. That will allow construction crews to finish paving the lanes connecting to a new northbound bridge over I-44.


View the full article: Oklahoman.com